Dashboard Update:

  • All projects at implementation stage with Green RAG Status
  • 3 red risks and 1 red Issue related to the SWIS Replacement (Liquidlogic) Project

Achievements

  • Significant progress on kitting out corporate connectivity for new Foundry office in Larbert
  • Newmarket Street and Central Hub also fitted out with connectivity and IT equipment

Finance

  • Savings reports have been produced from Integra for the Innovation Projects.
  • Change fund reports are being developed, some tweaks required. Will be clear on links to Projects.
  • New Integra financial reports are being developed to show sub-project detail. Senior accountants and project managers to work on further developing after 23/08/21.

12 Month Outlook

  • List being developed of all elected member decisions for Innovation projects due over the next 12 months

Change Control Process

  • Formal change control process is now in place for requests to update Milestone due dates.

Next meeting - 1 September