Dashboard Update
- 11 projects in Gateway 3, 2 in Gateway 2 and 1 in Gateway 1
- RAG status applied
- 3 projects are rated red
- 8 projects are rate green
- Risks and issues under continual review during project duration
Project Achievements
- Alternative Family Placement: Falkirk's young people have been the subject of a positive article in both national and local press
- Community Empowerment Action Team have agreed Terms of Reference
- Building & Maintenance Division awarded c£5m of roofing and roughcasting improvement works to c180 houses